ACHIEVEMENT OF
WORKS UNDER PWD BUILDING DIVISION, LUNGLEI SINCE 1999
| 1. |
Name
of work : Construction of District Revenue Building at Lunglei |
| |
a)
Sanctioned Amount |
: |
Rs.55,96,229.00 |
| |
b)
Expenditure |
: |
Rs.59,16,000.00 |
| |
c)
Date of commencement |
: |
18th
March 1997 |
| |
d)
Date of completion |
: |
7th
April 1999 |
| |
e)
Plinth area |
: |
424.00
Sqm |
| |
f)
Purpose |
: |
For
Office building since District Revenue had
no office building of their own at Lunglei |
| 2. |
Name
of work : Construction of Government College Science block at
Lunglei at Lunglei |
| |
a)
Sanctioned Amount |
: |
Rs.1,38,82,886.00 |
| |
b)
Expenditure |
: |
Rs.1,29,48,000.00 |
| |
c)
Date of commencement |
: |
18th
July 1996 |
| |
d)
Date of completion |
: |
16th
November 2000 |
| |
e)
Plinth area |
: |
1755.00
Sqm. |
| |
f)
Purpose |
: |
For
accommodation of Science student at Government
College, Lunglei. |
| 3 |
Name
of work : Construction of combined EE & SDO Quarter at
Chanmari, Lunglei |
| |
a)
Sanctioned Amount |
: |
Rs.20,80,974.00 |
| |
b)
Expenditure |
: |
Rs.20,18,000.00 |
| |
c)
Date of commencement |
: |
5th
July 1999 |
| |
d)
Date of completion |
: |
3rd
February 2001 |
| |
e)
Plinth area |
: |
191.60Sqm |
| |
f)
Purpose |
: |
For
accommodating SDOs and EE, PWD at Lunglei town |
| 4 |
Name
of work : Construction of Conservator of Forest Office
Building at Lunglei |
| |
a)
Sanctioned Amount |
: |
Rs.86,64,300.00 |
| |
b)
Expenditure |
: |
Rs.78,87,000.00 |
| |
c)
Date of commencement |
: |
18th
March 1997 |
| |
d)
Date of completion |
: |
Date
3rd October 2001 |
| |
e)
Plinth area |
: |
1284.00
Sqm |
| |
f)
Purpose |
: |
For
office building since Conservator of Forest had
no office building of their own at Lunglei |
| 5 |
Name
of work : Construction of combined EE & SDO Quarter at
Chanmari, Lunglei |
| |
a)
Sanctioned Amount |
: |
Rs.28,74,000.00 |
| |
b)
Expenditure |
: |
Rs.26,20,000.00 |
| |
c)
Date of commencement |
: |
8th
August 1997 |
| |
d)
Date of completion |
: |
8th
February 1999 |
| |
e)
Plinth area |
: |
380.00Sqm |
| |
f)
Purpose |
: |
For
accommodating more tourist at Lunglei |
| 6 |
Name
of work : Construction of PWD Mechanical Division Office at
Lunglei |
| |
a)
Sanctioned Amount |
: |
Rs.39,40,000.00 |
| |
b)
Expenditure |
: |
Rs.39,40,000.00 |
| |
c)
Date of commencement |
: |
18th
February 1997 |
| |
d)
Date of completion |
: |
14th
March 2001 |
| |
e)
Plinth area |
: |
680.50
Sqm. |
| |
f)
Purpose |
: |
For
PWD Mechanical Division Office since PWD
Mechanical Division had no office building
of their own at Lunglei. |
| 7 |
Name
of work : Construction of SDO Quarter 4-units at Rahsiveng
Lunglei |
| |
a)
Sanctioned Amount |
: |
Rs.32,99,024.00 |
| |
b)
Expenditure |
: |
Rs.32,18,000.00 |
| |
c)
Date of commencement |
: |
5th
July 1999 |
| |
d)
Date of completion |
: |
18th
February 2002 |
| |
e)
Plinth area |
: |
365.20
Sqm |
| |
f)
Purpose |
: |
For
accommodating four SDOs, PWD at Lunglei town |
| 8 |
Name
of work : Construction of JE Quarter 4-units at Rahsiveng,
Lunglei |
| |
a)
Sanctioned Amount |
: |
Rs.19,53,500.00 |
| |
b)
Expenditure |
: |
Rs.24,05,000.00 |
| |
c)
Date of commencement |
: |
5th
July 1999 |
| |
d)
Date of completion |
: |
15th
November 2001 |
| |
e)
Plinth area |
: |
287.30
Sqm |
| |
f)
Purpose |
: |
For
accommodating four JE's, PWD at Lunglei town |
| 9 |
Name
of work : Reconstruction of DC Office building at Lunglei Ph-I |
| |
a)
Sanctioned Amount |
: |
Rs.2,65,39,500.00 |
| |
b)
Expenditure |
: |
Rs.78,87,000.00 |
| |
c)
Date of commencement |
: |
19th
March 1997 |
| |
d)
Date of completion |
: |
31st
November 2001 |
| |
e)
Plinth area |
: |
1171.75
Sqm |
| |
f)
Purpose |
: |
Existing
DC Office building at Lunglei was very old and was of Assam
type building constructed back in 1930s. Reconstruction into
RCC building was felt needed |
| 10 |
Name
of work : Reconstruction of DC Office Building at Lunglei
Ph-II |
| |
a)
Sanctioned Amount |
: |
Rs.2,65,39,500.00 |
| |
b)
Expenditure |
: |
Rs.43,18,000.00 |
| |
c)
Date of commencement |
: |
18th
July 1999 |
| |
d)
Date of completion |
: |
4th
September 2001 |
| |
e)
Plinth area |
: |
458.80
Sqm |
| |
f)
Purpose |
: |
Existing DC Office building at Lunglei was
very old and was of Assam type building constructed back in
1930s. Reconstruction into RCC building was felt needed |
| 11 |
Name
of work : Construction of PWD Staff Quarter at Chanmari,
Lunglei |
| |
a)
Sanctioned Amount |
: |
Rs.15,66,000.00 |
| |
b)
Expenditure |
: |
Rs.13,73,000.00 |
| |
c)
Date of commencement |
: |
9th
July 1999 |
| |
d)
Date of completion |
: |
4th
February 2002 |
| |
e)
Plinth area |
: |
120.75
Sqm |
| |
f)
Purpose |
: |
For
accommodation PWD staff working at Lunglei town |
| 12 |
Name
of work : Construction of PWD Laboratory at Rahsiveng, Lunglei |
| |
a)
Sanctioned Amount |
: |
Rs.3,98,900.00 |
| |
b)
Expenditure |
: |
Rs.7,99,000.00 |
| |
c)
Date of commencement |
: |
16th
June 1999 |
| |
d)
Date of completion |
: |
16th
December 2000 |
| |
e)
Plinth area |
: |
118.44
Sqm |
| |
f)
Purpose |
: |
For installation of PWD Laboratory
equipments at Lunglei to facilitate materials testing for
better quality control for Souther Mizoram. |
| 13 |
Name
of work : Construction of DIET Boy's Hostel at Lunglei |
| |
a)
Sanctioned Amount |
: |
Rs.35,41,900.00 |
| |
b)
Expenditure |
: |
Rs.33,13,000.00 |
| |
c)
Date of commencement |
: |
5th
March 1997 |
| |
d)
Date of completion |
: |
13th
July 2001 |
| |
e)
Plinth area |
: |
615.00
Sqm |
| |
f)
Purpose |
: |
For
accommodation of DIET trainees at Lunglei |
| 14 |
Name
of work : Construction of DIET Girl's Hostel at Lunglei |
| |
a)
Sanctioned Amount |
: |
Rs.32,99,024.00 |
| |
b)
Expenditure |
: |
Rs.31,10,000.00 |
| |
c)
Date of commencement |
: |
5th
July 1999 |
| |
d)
Date of completion |
: |
11th
October 2001 |
| |
e)
Plinth area |
: |
446.00
Sqm. |
| |
f)
Purpose |
: |
For
accommodation of DIET trainees at Lunglei |
| 15 |
Name
of work : Construction of 200 bedded Civil Hospital at Lunglei
Ph-I |
| |
a)
Sanctioned Amount |
: |
Rs.4,60,70,000.00 |
| |
b)
Expenditure |
: |
Rs.1,68,59,000.00 |
| |
c)
Date of commencement |
: |
18th
March 1997 |
| |
d)
Date of completion |
: |
30th
May 2003 |
| |
e)
Up to date Progress |
: |
99.10% |
| |
e)
Plinth area |
: |
2976.96
Sqm |
| |
f)
Purpose |
: |
Civil Hospital building at Lunglei was very
old and was of Assam type building and hence construction work
is being taken up for new Hospital building for upgradation to
a 200-bedded Hospital |
| 16 |
Name
of work : Construction of 200 bedded Civil Hospital at Lunglei
Ph-II |
| |
a)
Sanctioned Amount |
: |
Rs.4,60,70,000.00 |
| |
b)
Expenditure |
: |
Rs.1,86,54,000.00 |
| |
c)
Date of commencement |
: |
26th
November 1999 |
| |
d)
Date of completion |
: |
31-Dec-03 |
| |
e)
Up to date Progress |
: |
62.00% |
| |
e)
Plinth area |
: |
4036.15
Sqm |
| |
f)
Purpose |
: |
Existing Civil Hospital building at Lunglei
is very old and hence construction work is being taken up for
New Hospital building. |
| 17 |
Name
of work : Construction of Medical Warehouse at Lunglei |
| |
a)
Sanctioned Amount |
: |
Rs.63,18,735.79 |
| |
b)
Expenditure |
: |
Rs.29,34,000.00 |
| |
c)
Date of commencement |
: |
6th
September 2002 |
| |
d)
Date of completion |
: |
31st
March 2003 |
| |
e)
Up to date Progress |
: |
80.00% |
| |
e)
Plinth area |
: |
837.00
Sqm |
| |
f)
Purpose |
: |
For atoning preserving medicine and other
important materials for Civil Hospital, Lunglei |
| 18 |
Name
of work : Construction of Saikuti Hall |
|
|
| |
a)
Sanctioned Amount |
: |
Rs.500,00,000.00 |
| |
b)
Expenditure |
: |
Rs.5,99,76,000.00 |
| |
c)
Date of commencement |
: |
20th
1995 |
| |
d)
Date of completion |
: |
31st
December 2003 |
| |
e)
Up to date Progress |
: |
97.00% |
| |
e)
Plinth area |
: |
5572.68
Sqcm |
| |
f)
Purpose |
: |
Community
and public |
| 19 |
Name
of work : Construction of Judicial Officers Quarter at Lunglei |
| |
a)
Sanctioned Amount |
: |
Rs.74,78,100.00 |
| |
b)
Expenditure |
: |
Rs.31,50,000.00 |
| |
c)
Date of commencement |
: |
5th
February 2002 |
| |
d)
Date of completion |
: |
31st
December 2003 |
| |
e)
Up to date Progress |
: |
27.00% |
| |
e)
Plinth area |
: |
550.00
Sqm |
| |
f)
Purpose |
: |
For accommodating Judicial Officers who are
working at Lunglei |
| 20 |
Name
of work : Construction of Information & Public Relation
Office at Lunglei |
| |
a)
Sanctioned Amount |
: |
Revised
A/A awaited |
| |
b)
Expenditure |
: |
Rs.12,50,000.00 |
| |
c)
Date of commencement |
: |
1st
November 2002 |
| |
d)
Date of completion |
: |
30th
October 2004 |
| |
e)
Up to date Progress |
: |
35.00% |
| |
e)
Plinth area |
: |
478.70Sqm |
| |
f)
Purpose |
: |
Existing I & PRO Office building at
Lunglei is very old and hence construction of new building is
being taken up |
|