 ACHIEVEMENT OF WORKS UNDER PWD BUILDING DIVISION, LUNGLEI SINCE 1999

1. Name of work : Construction of District Revenue Building at Lunglei
  a) Sanctioned Amount : Rs.55,96,229.00
  b) Expenditure : Rs.59,16,000.00
  c) Date of commencement : 18th March 1997
  d) Date of completion : 7th April 1999
  e) Plinth area : 424.00 Sqm
  f) Purpose :

For Office building since District Revenue had no office building of their own at Lunglei

2. Name of work : Construction of Government College Science block at Lunglei at Lunglei
  a) Sanctioned Amount : Rs.1,38,82,886.00
  b) Expenditure : Rs.1,29,48,000.00
  c) Date of commencement : 18th July 1996
  d) Date of completion : 16th November 2000
  e) Plinth area : 1755.00 Sqm.
  f) Purpose :

For accommodation of Science student at Government College, Lunglei.

3 Name of work : Construction of combined EE & SDO Quarter at Chanmari, Lunglei
  a) Sanctioned Amount : Rs.20,80,974.00
  b) Expenditure : Rs.20,18,000.00
  c) Date of commencement : 5th July 1999
  d) Date of completion : 3rd February 2001
  e) Plinth area : 191.60Sqm
  f) Purpose :

For accommodating SDOs and EE, PWD at Lunglei town

4 Name of work : Construction of Conservator of Forest Office Building at Lunglei
  a) Sanctioned Amount : Rs.86,64,300.00
  b) Expenditure : Rs.78,87,000.00
  c) Date of commencement : 18th March 1997
  d) Date of completion : Date 3rd October 2001
  e) Plinth area : 1284.00 Sqm
  f) Purpose :

For office building since Conservator of Forest had no office building of their own at Lunglei

5 Name of work : Construction of combined EE & SDO Quarter at Chanmari, Lunglei
  a) Sanctioned Amount : Rs.28,74,000.00
  b) Expenditure : Rs.26,20,000.00
  c) Date of commencement : 8th August 1997
  d) Date of completion : 8th February 1999
  e) Plinth area : 380.00Sqm
  f) Purpose : For accommodating more tourist at Lunglei
6 Name of work : Construction of PWD Mechanical Division Office at Lunglei
  a) Sanctioned Amount : Rs.39,40,000.00
  b) Expenditure : Rs.39,40,000.00
  c) Date of commencement : 18th February 1997
  d) Date of completion : 14th March 2001
  e) Plinth area : 680.50 Sqm.
  f) Purpose :

For PWD Mechanical Division Office since PWD Mechanical Division had no office building of their own at Lunglei.

7 Name of work : Construction of SDO Quarter 4-units at Rahsiveng Lunglei
  a) Sanctioned Amount : Rs.32,99,024.00
  b) Expenditure : Rs.32,18,000.00
  c) Date of commencement : 5th July 1999
  d) Date of completion : 18th February 2002
  e) Plinth area : 365.20 Sqm
  f) Purpose : For accommodating four SDOs, PWD at Lunglei town
8 Name of work : Construction of JE Quarter 4-units at Rahsiveng, Lunglei
  a) Sanctioned Amount : Rs.19,53,500.00
  b) Expenditure : Rs.24,05,000.00
  c) Date of commencement : 5th July 1999
  d) Date of completion : 15th November 2001
  e) Plinth area : 287.30 Sqm
  f) Purpose :

For accommodating four JE's, PWD at Lunglei town

9 Name of work : Reconstruction of DC Office building at Lunglei Ph-I
  a) Sanctioned Amount : Rs.2,65,39,500.00
  b) Expenditure : Rs.78,87,000.00
  c) Date of commencement : 19th March 1997
  d) Date of completion : 31st November 2001
  e) Plinth area : 1171.75 Sqm
  f) Purpose : Existing DC Office building at Lunglei was very old and was of Assam type building constructed back in 1930s. Reconstruction into RCC building was felt needed
10 Name of work : Reconstruction of DC Office Building at Lunglei Ph-II
  a) Sanctioned Amount : Rs.2,65,39,500.00
  b) Expenditure : Rs.43,18,000.00
  c) Date of commencement : 18th July 1999
  d) Date of completion : 4th September 2001
  e) Plinth area : 458.80 Sqm
  f) Purpose :

Existing DC Office building at Lunglei was very old and was of Assam type building constructed back in 1930s. Reconstruction into RCC building was felt needed

11 Name of work : Construction of PWD Staff Quarter at Chanmari, Lunglei
  a) Sanctioned Amount : Rs.15,66,000.00
  b) Expenditure : Rs.13,73,000.00
  c) Date of commencement : 9th July 1999
  d) Date of completion : 4th February 2002
  e) Plinth area : 120.75 Sqm
  f) Purpose :

For accommodation PWD staff working at Lunglei town

12 Name of work : Construction of PWD Laboratory at Rahsiveng, Lunglei
  a) Sanctioned Amount : Rs.3,98,900.00
  b) Expenditure : Rs.7,99,000.00
  c) Date of commencement : 16th June 1999
  d) Date of completion : 16th December 2000
  e) Plinth area : 118.44 Sqm
  f) Purpose :

For installation of PWD Laboratory equipments at Lunglei to facilitate materials testing for better quality control for Souther Mizoram.

13 Name of work : Construction of DIET Boy's Hostel at Lunglei
  a) Sanctioned Amount : Rs.35,41,900.00
  b) Expenditure : Rs.33,13,000.00
  c) Date of commencement : 5th March 1997
  d) Date of completion : 13th July 2001
  e) Plinth area : 615.00 Sqm
  f) Purpose : For accommodation of DIET trainees at Lunglei
14 Name of work : Construction of DIET Girl's Hostel at Lunglei
  a) Sanctioned Amount : Rs.32,99,024.00
  b) Expenditure : Rs.31,10,000.00
  c) Date of commencement : 5th July 1999
  d) Date of completion : 11th October 2001
  e) Plinth area : 446.00 Sqm.
  f) Purpose : For accommodation of DIET trainees at Lunglei
15 Name of work : Construction of 200 bedded Civil Hospital at Lunglei Ph-I
  a) Sanctioned Amount : Rs.4,60,70,000.00
  b) Expenditure : Rs.1,68,59,000.00
  c) Date of commencement : 18th March 1997
  d) Date of completion : 30th May 2003
  e) Up to date Progress : 99.10%
  e) Plinth area : 2976.96 Sqm
  f) Purpose :

Civil Hospital building at Lunglei was very old and was of Assam type building and hence construction work is being taken up for new Hospital building for upgradation to a 200-bedded Hospital

16 Name of work : Construction of 200 bedded Civil Hospital at Lunglei Ph-II
  a) Sanctioned Amount : Rs.4,60,70,000.00
  b) Expenditure : Rs.1,86,54,000.00
  c) Date of commencement : 26th November 1999
  d) Date of completion : 31-Dec-03
  e) Up to date Progress : 62.00%
  e) Plinth area : 4036.15 Sqm
  f) Purpose :

Existing Civil Hospital building at Lunglei is very old and hence construction work is being taken up for New Hospital building.

17 Name of work : Construction of Medical Warehouse at Lunglei
  a) Sanctioned Amount : Rs.63,18,735.79
  b) Expenditure : Rs.29,34,000.00
  c) Date of commencement : 6th September 2002
  d) Date of completion : 31st March 2003
  e) Up to date Progress : 80.00%
  e) Plinth area : 837.00 Sqm
  f) Purpose :

For atoning preserving medicine and other important materials for Civil Hospital, Lunglei

18 Name of work : Construction of Saikuti Hall    
  a) Sanctioned Amount : Rs.500,00,000.00
  b) Expenditure : Rs.5,99,76,000.00
  c) Date of commencement : 20th 1995
  d) Date of completion : 31st December 2003
  e) Up to date Progress : 97.00%
  e) Plinth area : 5572.68 Sqcm
  f) Purpose : Community   and public
19 Name of work : Construction of Judicial Officers Quarter at Lunglei
  a) Sanctioned Amount : Rs.74,78,100.00
  b) Expenditure : Rs.31,50,000.00
  c) Date of commencement : 5th February 2002
  d) Date of completion : 31st December 2003
  e) Up to date Progress : 27.00%
  e) Plinth area : 550.00 Sqm
  f) Purpose :

For accommodating Judicial Officers who are working at Lunglei

20 Name of work : Construction of Information & Public Relation Office at Lunglei
  a) Sanctioned Amount : Revised A/A awaited
  b) Expenditure : Rs.12,50,000.00
  c) Date of commencement : 1st November 2002
  d) Date of completion : 30th October 2004
  e) Up to date Progress : 35.00%
  e) Plinth area : 478.70Sqm
  f) Purpose :

Existing I & PRO Office building at Lunglei is very old and hence construction of new building is being taken up