1 - BY  MECHANICAL  TRANSPORT

( Including loading, unloading and stacking etc.

    Gross Net   CARRIAGE  RATE  PER  UNIT  QUANTITY  FOR  A  LEAD  OF
Sl   Capacity Quantity Unit           Beyond
No Materials per after of           5 km
    Trip deduction Rates 1 km 2 km 3 km 4 km 5 km per unit
      of voids             per km
1 2 3 4 3 4 5 6 7 8 9
                   
1 a) Lime, moorum,                  
building rubbish. 6.00 6.00 cum 141.08 154.91 168.39 181.13 193.18 8.34
  b) Earth. 6.00 4.80 cum 176.34 193.63 210.49 226.42 241.48 10.43
  c) Manure or                  
sludge. 6.00 5.52 cum 153.34 168.38 183.04 196.88 209.98 9.07
  d) Excavated rock. 6.00 3.00 cum 282.15 309.81 336.79 362.27 386.37 16.69
  e) Sand, aggregate                  
below 40mm 5.00 5.00 cum 169.29 185.89 202.07 217.36 231.82 10.01
nominal size.                  
  f ) Aggregate                  
40mm nominal 5.00 4.62 cum 183.21 201.18 218.69 235.24 250.89 10.83
size and above.                  
  g) Stone boulder. 5.00 4.25 cum 199.16 218.69 237.73 255.72 272.73 11.78
  h) Concrete block. 3.00 3.00 cum 282.15 309.81 336.79 362.27 386.37 16.69
  i ) Brick. 2000 2000 1000nos 423.23 464.72 505.18 543.40 579.55 25.03
  j ) Brick tile,                  
roofing tile. 3200 3200 1000nos 264.52 290.45 315.74 339.63 362.22 15.64
  k) Steam coal. 5.50 5.50 ton 153.90 168.99 183.70 197.60 210.75 9.10
  l ) Empty cement                  
bag. 2000 2000 1000nos 423.23 464.72 505.18 543.40 579.55 25.03
                     
2 a) Steel. 7.00 7.00 ton 120.92 132.78 144.34 155.26 165.59 7.15
  b) Timber. 5.00 5.00 cum 169.29 185.89 202.07 217.36 231.82 10.01
  c) Tar, bitumen,                  
roofing felt,                  
flooring felt, 4.50 4.50 ton 188.10 206.54 224.53 241.51 257.58 11.12
asphalt, etc.                  
  d) Cement, stone                  
block, GI, CC, CI                  
& AC pipes below                  
100mm dia and 7.00 7.00 ton 120.92 132.78 144.34 155.26 165.59 7.15
other heavy mate-                  
rials.                  
  e ) Glass block                  
(hollow) 200x 1000 1000 100nos 84.65 92.94 101.04 108.68 115.91 5.01
200x100mm.                  
                   
                   
3 a) RCC pipe, steel                  
cylinder, CI pipe,                  
RC pipe, unrein-                  
forced cement pipe,                  
prestressed con-                  
crete pipes.                  
  i) 100mm dia. 80x3.66m 292.80 m 2.89 3.17 3.45 3.71 3.96 0.17
  ii) 125mm dia. 60x3.66m 219.60 m 3.85 4.23 4.60 4.95 5.28 0.23
  iii) 150mm dia. 50x3.66m 183.00 m 4.63 5.08 5.52 5.94 6.33 0.27
  iv) 200mm dia. 30x3.66m 109.80 m 7.71 8.46 9.20 9.90 10.56 0.46
  v) 250mm dia. 22x3.66m 80.52 m 10.51 11.54 12.55 13.50 14.40 0.62
  vi) 300mm dia. 17x3.66m 62.22 m 13.60 14.94 16.24 17.47 18.63 0.80
  vii) 350mm dia. 12x3.66m 43.92 m 19.27 21.16 23.00 24.74 26.39 1.14
  viii) 400mm dia. 9x3.66m 32.94 m 25.70 28.22 30.67 32.99 35.19 1.52
  ix) 450mm and                  
500mm dia. 7x3.66m 25.62 m 33.04 36.28 39.44 42.42 45.24 1.95
  x) 600, 700, 750,                  
and 800mm dia. 5x3.66m 18.30 m 46.25 50.79 55.21 59.39 63.34 2.74
  xi) 900mm dia. 3x3.66m 10.98 m 77.09 84.65 92.02 98.98 105.56 4.56
  xii) 1000, 1100,                  
  and 1200mm dia. 2x3.66m 7.32 m 115.64 126.97 138.03 148.47 158.35 6.84
  b) RCC Hume pipes                  
  i ) NP3 900mm dia. 4x2.5m 10.00 m 84.65 92.94 101.04 108.68 115.91 5.01
  ii) NP3 1200mm dia. 3x2.5m 10.00 m 84.65 92.94 101.04 108.68 115.91 5.01
                     
  c) SW pipes.                  
  i) 100mm dia. 800x0.6m 480.00 m 1.76 1.94 2.10 2.26 2.41 0.10
  ii) 150mm dia. 400x0.6m 240.00 m 3.53 3.87 4.21 4.53 4.83 0.21
  iii) 200mm dia. 225x0.6m 135.00 m 6.27 6.88 7.48 8.05 8.59 0.37
  iv) 230mm dia. 175x0.6m 105.00 m 8.06 8.85 9.62 10.35 11.04 0.48
  v) 250mm dia. 140x0.6m 84.00 m 10.08 11.06 12.03 12.94 13.80 0.60
  vi) 300mm dia. 110x0.6m 66.00 m 12.83 14.08 15.31 16.47 17.56 0.76
  vii) 350mm dia. 80x0.6m 48.00 m 17.63 19.36 21.05 22.64 24.15 1.04
  viii) 400mm dia. 55x0.6m 33.00 m 25.65 28.16 30.62 32.93 35.12 1.52
  ix) 450mm dia 45x0.6m 27.00 m 31.35 34.42 37.42 40.25 42.93 1.85
  x) 500mm dia. 40x0.6m 24.00 m 35.27 38.73 42.10 45.28 48.30 2.09
  x) 600mm dia. 30x0.6m 18.00 m 47.03 51.64 56.13 60.38 64.39 2.78
NOTES :                  
1 The carriage rates are of loose quantity of materials, i.e. before deduction of voids if any.
2 Analysis based on CPWD Analysis of Rates 1997, Vol - I      

Back

 

Developed, Designed and Hosted by
National Informatics Centre, Mizoram State Unit
with the contents provided by Public Works Department, Government of Mizoram