7 - CULVERTS |
|
Sl No |
Description |
Unit |
Rate |
|
|
|
|
|
|
|
57 |
Cement concrete 1:4:8 mix with stone aggregate 40 mm nominal size in
foundation upto a depth of 1.5 metres below ground level and upto
height of 1.50 metres above ground/bed level. |
cum |
Rs.2,503.50 |
|
|
|
(Rupees two thousand five hundred three and paise fifty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
58 |
Cement concrete 1:3:6 mix with stone aggregates 20 mm nominal size
mechanically mixed and vibrated in foundation upto a depth of 1.5
metres below ground level and 1.50 metres above ground/bed level. |
cum |
Rs.2,814.80 |
|
|
|
(Rupees two thousand eight hundred fourteen and paise eighty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
59 |
Plain cement concrete M15 mix with stone aggregates 20 mm nominal size
mechanically mixed and vibrated in foundation upto a depth of 1.50
metres below ground level and/or 1.50 metres above ground/bed level. |
cum |
Rs.3,384.30 |
|
|
|
(Rupees three thousand three hundred eighty four and paise thirty)
only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
60 |
Plain cement concrete M15 mix with stone aggregate 20mm nominal size
mechanically mixed and vibrated in superstructure upto 4 metres above,
1.5 metres from bed/ground level. |
cum |
Rs.3,436.30 |
|
|
|
(Rupees three thousand four hundred thirty six and paise thirty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
61 |
Reinforced cement concrete M20 mix with stone aggregate 20 mm nominal
size mechanically mixed and vibrated for reinforced concrete work in
slab excluding steel reinforcement, but including centering and
shuttering, laid in position. |
cum |
Rs.4,620.20 |
|
|
|
(Rupees four thousand six hundred twenty and paise twenty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
62 |
Reinforced cement concrete M20 mix with stone aggregate 20 mm nominal
size mechanically mixed and vibrated for bed plates excluding steel
reinforcement, but including centering and shuttering, laid in
position. |
cum |
Rs.4,385.30 |
|
|
|
(Rupees four thousand three hundred eighty five and paise thirty)
only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
63 |
Steel reinforcement for R.C.C works including bending, binding and
placing in position. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
Mild steel and medium tensile steel bars. |
tonne |
Rs.30,150.10 |
|
|
|
|
(Rupees thirty thousand one hundred fifty and paise ten) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(b) |
HYSD bars. |
tonne |
Rs.29,113.80 |
|
|
|
|
|
(Rupees twenty nine thousand one hundred thirteen and paise eighty)
only. |
|
|
|
|
|
|
|
|
|
|
|
|
64 |
First class brick in cement mortar 1:3 upto a depth of 1.50 metres
below ground and above 1.50 bed/ground level. |
cum |
Rs.3,670.90 |
|
|
|
(Rupees three thousand six hundred seventy and paise ninety) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
65 |
Extra for brick work in superstructure upto a height of 4 metres or
part thereof above 1.5 metre from bed/ground level. |
cum |
Rs.78.70 |
|
|
|
(Rupees seventy eight and paise seventy) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
66 |
Brick flooring with 1st class bricks including cement slurry in cement
sand mortar 1 : 4. |
sqm |
Rs.389.40 |
|
|
|
(Rupees three hundred eighty nine and paise forty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
67 |
Coursed rubble stone masonry in cement sand mortar 1:3 in foundation
upto a depth of 1.50 metres and also 1.50 metres above ground/bed
level. |
cum |
Rs.3,579.50 |
|
|
|
(Rupees three thousand five hundred seventy nine and paise fifty)
only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
68 |
Extra for coursed rubble masonry in superstructure upto a height of 4
metres or part thereof above 1.50 metres from ground/bed level. |
cum |
Rs.117.20 |
|
|
|
(Rupees one hundred seventeen and paise twenty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
69 |
Random rubble masonry (coursed) in cement sand mortar 1:3 in
foundation upto a depth of 1.50 metres and 1.50 above ground/bed
level. |
cum |
Rs.3,360.40 |
|
|
|
(Rupees three thousand three hundred sixty and paise forty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
70 |
Extra for random rubble masonry (coursed) in cement sand mortar 1 : 3
in superstructure upto a height of 4 metres or part thereof, 1.50
metres from ground/bed level. |
cum |
Rs.117.20 |
|
|
|
(Rupees one hundred seventeen and paise twenty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
71 |
Cement pointing 1 : 2 deep variety (cut or weather) on brick and tile
work. |
sqm |
Rs.50.70 |
|
|
|
(Rupees fifty and paise seventy) only. |
|
|
|
|
|
|
|
|
|
|
|
|
72 |
Cement pointing 1 : 2 flush on brick on edge floor. |
sqm |
Rs.54.50 |
|
|
|
(Rupees fifty four and paise fifty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
73 |
Cement plaster 12 mm thick in cement mortar 1 : 3. |
sqm |
Rs.94.40 |
|
|
|
(Rupees ninety four and paise forty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
74 |
Dry boulder pitching in flooring. |
cum |
Rs.844.30 |
|
|
|
(Rupees eight hundred forty four and paise thirty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
75 |
Making and filling expansion joints, with bitumen filler (bitumen 40%,
asbestos 5% and sand 55%) 12 mm wide. |
per metre per cm |
Rs.0.90 |
|
|
(Paise ninety) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
76 |
Providing and laying 900mm RCC Hume Pipe NP 3 class without collar and
jointing ends with cement mortar 1:2 complete. |
Rm |
Rs.5,840.00 |
|
|
|
(Rupees five thousand eight hundred forty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
77 |
Providing and laying 900mm RCC Hume Pipe NP 2 class with collar with
stiff mixture of cement mortar in the proportion of 1:2 including
jointing, filling mortar between the pipe and collar, etc. |
Rm |
Rs.3,115.00 |
|
|
|
(Rupees three thousand one hundred fifteen) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
78 |
Providing and laying ARMCO culvert of size 885mm x 2200mm made of
0.63mm thickness G.C.I sheet cut into 2 (two)
pieces and made semi-circular and 5 cm bent at right angle at ends and
jointed together with nuts and bolts. |
Rm |
Rs.987.60 |
|
|
|