1 - SITE CLEARANCE |
|
Sl No |
Description |
Unit |
Rate |
|
7 |
Clearing grass and removal of rubbish upto a distance of 50
metres outside the periphery of the area cleared. By manual means . |
sqm |
Rs.0.62 |
|
|
|
(Paise sixty two) only. |
|
|
|
|
|
|
|
|
8 |
Clearing and grubbing road land including uprooting rank vegetation,
grass, brush shrubs, saplings and trees of girth upto 300 mm, removal
of stumps, disposal of unserviceable material and stacking of
serviceable material upto 100 metres from road boundary. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
By manual means. |
|
|
|
|
|
i ) In area of light jungle. |
sqm |
Rs.2.48 |
|
|
|
|
|
(Rupees two and paise forty eight) only. |
|
|
|
ii ) In area of thorny jungle. |
sqm |
Rs.3.71 |
|
|
|
|
|
(Rupees three and paise seventy one) only. |
|
|
|
|
|
|
|
(b) |
By mechanical means. |
sqm |
Rs.1.68 |
|
|
|
( for all classes of jungle ). |
|
(Rupees one and paise sixty eight) only. |
|
9 |
Clearing jungle including uprooting of rank vegetation, grass, brush
wood, trees and saplings of girth upto 30cm measured at a height of 1m
above ground level and removal of rubbish upto a distance of 50 metres
outside the periphery of the area cleared. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
By manual means. |
|
|
|
|
|
(i) Light jungle. |
sqm |
Rs.1.92 |
|
|
|
|
|
(Rupees one and paise ninety two) only. |
|
|
|
|
|
|
|
|
(ii) Medium jungle. |
sqm |
Rs.2.88 |
|
|
|
|
|
(Rupees two and paise eighty eight) only. |
|
|
|
|
|
|
|
|
(iii) Heavy jungle. |
sqm |
Rs.3.84 |
|
|
|
|
|
(Rupees three and paise eighty four) only. |
|
|
|
|
|
|
10 |
Cutting of trees including cutting of trunks, branches and removal of
stumps including stacking of serviceable materials within a lead of
100 metres and eart filling in the depression/pit. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
Girth above 30 cm to 60 cm. |
no |
Rs.76.28 |
|
|
|
|
|
(Rupees seventy six and paise twenty eight) only. |
|
|
|
|
|
|
|
(b) |
Girth above 60 cm to 90 cm. |
no |
Rs.149.73 |
|
|
|
|
|
(Rupees one hundred forty nine and paise seventy three) only. |
|
|
|
|
|
|
|
(c) |
Girth above 90 cm to 180 cm. |
no |
Rs.381.38 |
|
|
|
|
|
(Rupees three hundred eighty one and paise thirty eight) only. |
|
|
|
|
|
|
|
(d) |
Girth above 180 cm to 270 cm. |
no |
Rs.635.63 |
|
|
|
|
|
(Rupees six hundred thirty five and paise sixty three) only. |
|
|
|
|
|
|
|
(e) |
Girth above 270 cm. |
no |
Rs.1,525.50 |
|
|
|
|
|
(Rupees one thousand five hundred twenty five and paise fifty) only. |
|
11 |
Felling, uprooting and removal of big bamboo clumps
(girth measured at 1m above ground level). |
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
Girth from 270 cm to 1100 cm. |
no |
Rs.228.70 |
|
|
|
|
|
(Rupees two hundred twenty eight and paise seventy) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(b) |
Girth above 1100 cm. |
no |
Rs.343.00 |
|
|
|
|
|
(Rupees three hundred forty three) only. |
|
|
Note : |
Bamboo clumps of girth less than 270cm shall be included under normal
Clearing of jungle item. |
|
|
|
|
|
|
|
|
12 |
Clearing road side vegetation, brush shrubs, mooli bamboos, overgrown
grass etc. including removal of rubbish away from existing road
formation. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
Light vehicle road. |
km |
Rs.1,171.90 |
|
|
|
|
|
(Rupees one thousand one hundred seventy one and paise ninety) only. |
|
|
|
|
|
|
|
(b) |
Medium truck road (VR, ODR, etc.) |
km |
Rs.2,172.30 |
|
|
|
|
|
(Rupees two thousand one hundred seventy two and paise thirty) only. |
|
|
|
|
|
|
|
(c) |
MDR, SH and NH, etc. |
km |
Rs.2,944.00 |
|
|
|
|
|
(Rupees two thousand nine hundred forty four) only. |
|
|
|
|
|
|
13 |
Clearing landslips including removal of spoils upto 30m. |
|
|
|
|
|
|
|
|
( for recently deposited earthwork ). |
|
|
|
|
(a) |
Ordinary soil. |
cum |
Rs.30.10 |
|
|
|
|
|
(Rupees thirty and paise ten) only. |
|
|
|
|
|
|
|
(b) |
Rock debris ( blasting not required ). |
cum |
Rs.45.60 |
|
|
|
|
|
(Rupees forty five and paise sixty) only. |
|
|
|
|
|
|
|
(c) |
Rocks ( blasting required ). |
cum |
Rs.145.40 |
|
|
|
|
|
(Rupees one hundred forty five and paise forty) only. |
|
|
|
|
|
|
|
(d) |
Rocks ( chiseling works required ). |
|
Rs.272.00 |
|
|
|
|
|
(Rupees two hundred seventy two) only. |
|
|
|
|
|
|
|
Note : |
Earthwork for landslips deposited before monsoon which has had full