7 - BRICK WORK |
|
Sl No |
Description |
Unit |
Rate |
|
|
|
|
|
|
|
187 |
First class brickwork in cement mortar 1:3
(1 cement : 3 fine sand) including curing,
etc. complete. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
in foundation and plinth. |
cum |
Rs.3,893.80 |
|
|
|
|
|
(Rupees three thousand eight hundred ninety three and paise eighty)
only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(b) |
in superstructure above plinth level upto floor five level. |
cum |
Rs.4,137.70 |
|
|
|
|
(Rupees four thousand one hundred thirty seven and paise seventy)
only. |
|
|
|
|
|
|
|
|
|
|
|
|
188 |
First class brickwork in cement mortar 1:4
(1 cement : 4 fine sand)
including curing, etc. complete. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
in foundation and plinth. |
cum |
Rs.3,708.90 |
|
|
|
|
|
(Rupees three thousand seven hundred eight and paise ninety) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(b) |
in superstructure above plinth level upto floor five level. |
cum |
Rs.3,952.90 |
|
|
|
|
(Rupees three thousand nine hundred fifty two and paise ninety) only. |
|
|
|
|
|
|
|
|
|
|
|
|
189 |
First class brickwork in cement mortar 1:6
(1 cement : 6 fine sand)
including curing, etc. complete. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
in foundation and plinth. |
cum |
Rs.3,524.00 |
|
|
|
|
|
(Rupees three thousand five hundred twenty four) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(b) |
in superstructure above plinth level upto floor five level. |
cum |
Rs.3,768.00 |
|
|
|
|
(Rupees three thousand seven hundred sixty eight) only. |
|
|
|
|
|
|
|
|
|
|
|
|
190 |
Extra for brickworks in superstructure above floor five level
for every four floors or part thereof. |
cum |
Rs.16.50 |
|
|
|
(Rupees sixteen and paise fifty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
191 |
First class brickwork in plain arches in cement mortar 1:3 in
superstructure including centering and shuttering for span upto 6m
including curing, etc. complete. |
cum |
Rs.5,316.40 |
|
|
|
(Rupees five thousand three hundred sixteen and paise forty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
192 |
First class brickwork in gauged arches in cement mortar 1:3 in
superstructure including centering and shuttering for span upto 6m
including curing, etc. complete. |
cum |
Rs.6,030.80 |
|
|
|
(Rupees six thousand thirty and paise eighty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
193 |
Half brick masonry with first class brick in cement mortar
1:3 (1 cement : 3 fine sand)
including curing, etc. complete. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
in foundation and plinth. |
sqm |
Rs.452.20 |
|
|
|
|
|
(Rupees four hundred fifty two and paise twenty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(b) |
in superstructure above plinth level upto floor five level. |
sqm |
Rs.480.60 |
|
|
|
|
(Rupees four hundred eighty and paise sixty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
194 |
Half brick masonry with first class brick in cement mortar
1:4 (1 cement : 4 fine sand)
including curing, etc. complete. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
in foundation and plinth. |
sqm |
Rs.431.50 |
|
|
|
|
|
(Rupees four hundred thirty one and paise fifty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(b) |
in superstructure above plinth level upto floor five level. |
sqm |
Rs.459.90 |
|
|
|
|
(Rupees four hundred fifty nine and paise ninety) only. |
|
|
|
|
|
|
|
|
|
|
|
|
195 |
Extra for half brick masonry in superstructure above floor five
level for every four floors or part thereof. |
sqm |
Rs.19.20 |
|
|
|
(Rupees nineteen and paise twenty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
196 |
Extra for providing and placing in position 2 nos 6mm dia. MS bars at
every third course of half brick masonry. |
sqm |
Rs.36.70 |
|
|
|
(Rupees thirty six and paise seventy) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
197 |
Honey-comb half brick masonry with first class brick in
cement mortar 1:3 including curing, etc. complete . |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
in foundation and plinth. |
sqm |
Rs.298.50 |
|
|
|
|
|
(Rupees two hundred ninety eight and paise fifty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(b) |
in superstructure above plinth level upto floor five level. |
sqm |
Rs.317.20 |
|
|
|
|
(Rupees three hundred seventeen and paise twenty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
198 |
Honey-comb half brick masonry with first class brick in
cement mortar 1:4 including curing, etc. complete . |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
in foundation and plinth. |
sqm |
Rs.284.30 |
|
|
|
|
|
(Rupees two hundred eighty four and paise thirty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(b) |
in superstructure above plinth level upto floor five level. |
sqm |
Rs.303.00 |
|
|
|
|
(Rupees three hundred three) only. |
|
|
|
|
|
|
|
|
|
|
|
|
199 |
7.5 cm thick brick masonry with first class brick in cement
mortar 1:3 (1cement : 3 fine sand)
including curing, etc. complete . |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
in superstructure above plinth level upto floor five level. |
sqm |
Rs.322.40 |
|
|
|
|
(Rupees three hundred twenty two and paise forty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
200 |
7.5 cm thick brick masonry with first class brick in cement
mortar 1:4 (1cement : 4 fine sand)
including curing, etc. complete . |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
in superstructure above plinth level upto floor five level. |
sqm |
Rs.309.00 |
|
|
|
|
(Rupees three hundred nine) only. |
|
|
|
|
|
|
|
|
|
|
|
|
201 |
Extra for 7.5 cm thick brick masonry in superstructure above floor
five level for every four floors or part thereof. |
sqm |
Rs.12.80 |
|
|
|
(Rupees twelve and paise eighty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
202 |
Extra for providing and placing in position 2 nos 6mm dia. MS bars at
every third course of 7.5 cm thick brick masonry. |
sqm |
Rs.25.00 |
|
|
|
(Rupees twenty five) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
203 |
Reduction for using second class brick instead of first class brick in
brick masonry. |
cum |
Rs.219.80 |
|
|
|
(Rupees two hundred nineteen and paise eighty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
204 |
Reduction for using second class brick instead of first class brick in
half brick masonry. |
sqm |
Rs.25.10 |
|
|
|
(Rupees twenty five and paise ten) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
205 |
Reduction for using second class brick instead of first class
brick in 7.50cm thick masonry. |
sqm |
Rs.16.80 |
|
|
|
(Rupees sixteen and paise eighty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
206 |
Dry brick pitching half brick thick in drains with first class brick
including supply of bricks and preparing surface complete. |
sqm |
Rs.350.50 |
|
|
|
(Rupees three hundred fifty and paise fifty) only. |
|
|
|