1 - EARTHWORK |
|
Sl No |
Description |
Unit |
Rate |
|
|
|
|
|
|
|
|
Notes : |
|
|
|
|
|
1 |
For items of Site Clearance & Earthwork not included in Part D, |
|
|
|
please refer to respective chapters under Part B. |
|
|
|
|
|
|
|
127 |
Earthwork in excavation to get the desired levels and areas and
dressing of the surface by manual means including disposal of
excavated earth by using it for filling and dressing wherever required
within a lead of 15m and lift upto 1.5m. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
Ordinary soil |
cum |
Rs.72.40 |
|
|
|
|
|
(Rupees seventy two and paise forty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(b) |
Hard soil ( pick work ). |
cum |
Rs.94.50 |
|
|
|
|
|
(Rupees ninety four and paise fifty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(c) |
Soft Rock ( blasting work ). |
cum |
Rs.237.00 |
|
|
|
|
|
(Rupees two hundred thirty seven) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(d) |
Hard Rock ( blasting work ). |
cum |
Rs.329.70 |
|
|
|
|
|
(Rupees three hundred twenty nine and paise seventy) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(e) |
Chiselling/ wedging out rock where blasting is prohibited. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(i) Soft Rock. |
cum |
Rs.417.90 |
|
|
|
|
|
(Rupees four hundred seventeen and paise ninety) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(ii) Hard Rock. |
cum |
Rs.625.80 |
|
|
|
|
|
(Rupees six hundred twenty five and paise eighty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
128 |
Earthwork in excavation in foundation trenches etc. not exceeding 2
meters depth including dressing of bottom and sides of trenches and
subsequent filling as in column foundations, fence posts, etc. and
disposal of all surplus soil as directed within a lead of 30 metres. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
Ordinary Soil. |
cum |
Rs.85.00 |
|
|
|
|
|
(Rupees eighty five) only. |
|
|
|
|
|
|
|
(b) |
Hard Soil ( pick work ). |
cum |
Rs.127.50 |
|
|
|
|
|
(Rupees one hundred twenty seven and paise fifty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(c) |
Very Hard Soil ( jumper work ). |
cum |
Rs.198.30 |
|
|
|
|
|
(Rupees one hundred ninety eight and paise thirty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(d) |
Soft Rock ( blasting work ). |
cum |
Rs.278.70 |
|
|
|
|
|
(Rupees two hundred seventy eight and paise seventy) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(e) |
Hard Rock ( blasting work ). |
cum |
Rs.387.70 |
|
|
|
|
|
(Rupees three hundred eighty seven and paise seventy) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(f) |
Chiselling/ wedging out rock where blasting is prohibited. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(i) Soft Rock. |
cum |
Rs.596.30 |
|
|
|
|
|
(Rupees five hundred ninety six and paise thirty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(ii) Hard Rock |
cum |
Rs.944.60 |
|
|
|
|
|
(Rupees nine hundred forty four and paise sixty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
129 |
Filling available excavated earth (excluding rock)
in trenches, plinth, etc. in layers not exceeding 20 cms in
depth, consolidating each layer by ramming and watering and
dressing lead upto 50 meters and lift upto 1.50 meters. |
cum |
Rs.32.00 |
|
|
|
(Rupees thirty two) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
130 |
Providing and filling stone aggregates of size below 90mm in plinth,
etc. in layers not exceeding 20 cms in depth,
consolidating each layer by ramming and watering and dressing
complete. |
cum |
Rs.994.90 |
|
|
|
(Rupees nine hundred ninety four and paise ninety) only. |
|
|
|
|
|
|
|
|
|
|
|
|
131 |
Providing and filling approved river sand in trenches, plinth, etc. in
layers not exceeding 20 cms in depth, consolidating each
layer by ramming and watering and dressing complete. |
cum |
Rs.958.50 |
|
|
|
(Rupees nine hundred fifty eight and paise fifty) only. |
|
|
|
|
|
|
|
|
|
|
|