Sl No |
Description |
Unit |
Rate |
|
|
|
|
|
|
|
14 |
Earthwork in excavation exclusive of compensation of earth in - |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
Ordinary soil. |
|
|
|
|
|
|
|
|
|
|
|
(i) Kassi work undressed involving an average horizontal throw
upto 2 metres and an average vertical lift upto 0.50 metres
including breaking of clods. |
cum |
Rs.32.30 |
|
|
|
|
(Rupees thirty two and paise thirty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(ii) Earthwork with combined lead upto 15 metres including
breaking of clods. |
cum |
Rs.43.10 |
|
|
|
|
(Rupees forty three and paise ten) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(b) |
Hard soil ( pick work ). |
cum |
Rs.65.10 |
|
|
|
|
|
(Rupees sixty five and paise ten) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(c) |
Soft Rock ( blasting work ). |
cum |
Rs.208.00 |
|
|
|
|
|
(Rupees two hundred eight) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(d) |
Hard Rock ( blasting work ). |
cum |
Rs.301.00 |
|
|
|
|
|
(Rupees three hundred one) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(e) |
Chiselling/ wedging out rock where blasting is prohibited. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(i) Soft Rock. |
cum |
Rs.388.60 |
|
|
|
|
|
(Rupees three hundred eighty eight and paise sixty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(ii) Hard Rock. |
cum |
Rs.596.50 |
|
|
|
|
|
(Rupees five hundred ninety six and paise fifty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
( f ) |
Marshy soil including pumping out water, removal of the same and
disposal within a lead of 15 metres. |
|
|
|
|
|
cum |
Rs.64.60 |
|
|
|
|
(Rupees sixty four and paise sixty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
15 |
Extra for additional lead as in through cutting or when
excavated earth/ rock etc. can not be disposed of directly to
valley below, by manual means (when lead is
more than 15m). |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
Ordinary and Hard Soil. |
|
|
|
|
|
|
|
|
|
|
|
(i) When over all lead is upto 50m. |
cum |
Rs.30.10 |
|
|
|
|
|
(Rupees thirty and paise ten) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(ii) When over all lead is upto 100m. |
cum |
Rs.66.80 |
|
|
|
|
|
(Rupees sixty six and paise eighty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(b) |
Soft and Hard rock. |
|
|
|
|
|
|
|
|
|
|
|
(i) When over all lead is upto 50m. |
cum |
Rs.48.20 |
|
|
|
|
|
(Rupees forty eight and paise twenty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(ii) When over all lead is upto 100m. |
cum |
Rs.106.90 |
|
|
|
|
|
(Rupees one hundred six and paise ninety) only. |
|
|
|
|
|
|
|
|
|
|
|
|
16 |
Earthwork in surface excavation and dressing including cutting
and filling upto 15 cm depth, disposal of excavated earth upto
50m and lift upto 1.5m. |
sqm |
Rs.14.70 |
|
|
|
(Rupees fourteen and paise seventy) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
17 |
Earthwork in excavation in foundation trenches, drains, etc. not
exceeding 2 meters depth including dressing of bottom and sides
of trenches and disposal of all surplus soil as directed within
a lead of 30 metres. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
Oridinary Soil |
cum |
Rs.68.00 |
|
|
|
|
|
(Rupees sixty eight) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(b) |
Hard Soil ( pick work ) |
cum |
Rs.102.00 |
|
|
|
|
|
(Rupees one hundred two) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(c) |
Very Hard Soil ( jumper work ). |
cum |
Rs.158.60 |
|
|
|
|
|
(Rupees one hundred fifty eight and paise sixty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(d) |
Soft Rock ( blasting work ). |
cum |
Rs.223.20 |
|
|
|
|
|
(Rupees two hundred twenty three and paise twenty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(e) |
Hard Rock ( blasting work ). |
cum |
Rs.310.60 |
|
|
|
|
|
(Rupees three hundred ten and paise sixty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
( f ) |
Chiselling/ wedging out rock where blasting is prohibited. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(i) Soft Rock. |
cum |
Rs.477.00 |
|
|
|
|
|
(Rupees four hundred seventy seven) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(ii) Hard Rock |
cum |
Rs.755.70 |
|
|
|
|
|
(Rupees seven hundred fifty five and paise seventy) only. |
|
|
|
|
|