2 - FOUNDATION |
|
Sl No |
Description |
Unit |
Rate |
|
|
|
|
|
|
|
101 |
Brick masonry work in cement mortar 1:3 in foundation complete
excluding pointing and plastering, as per drawing and Technical
Specifications. |
cum |
Rs.5,028.70 |
|
|
|
(Rupees five thousand twenty eight and paise seventy) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
102 |
Stone masonry work in cement mortar 1:3 for foundation complete
as per drawing and Technical Specifications. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
Coursed Rubble Masonry (first sort). |
cum |
Rs.3,526.50 |
|
|
|
|
|
(Rupees three thousand five hundred twenty six and paise fifty)
only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(b) |
Random Rubble Masonry (coursed / uncoursed). |
cum |
Rs.3,637.50 |
|
|
|
|
(Rupees three thousand six hundred thirty seven and paise fifty)
only. |
|
|
|
|
|
|
|
|
|
|
|
|
103 |
Cement concrete for plain concrete / reinforced concrete in open
foundation as per drawing & Technical Specifications. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
M 15 grade in P.C.C. |
cum |
Rs.4,109.10 |
|
|
|
|
|
(Rupees four thousand one hundred nine and paise ten) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(b) |
M 20 grade in P.C.C. |
cum |
Rs.4,532.40 |
|
|
|
|
|
(Rupees four thousand five hundred thirty two and paise forty)
only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(c) |
M 20 grade in R.C.C. |
cum |
Rs.4,737.40 |
|
|
|
|
|
(Rupees four thousand seven hundred thirty seven and paise
forty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(d) |
M 25 grade in R.C.C. |
cum |
Rs.4,955.00 |
|
|
|
|
|
(Rupees four thousand nine hundred fifty five) only. |
|
|
|
|
|
|
|
|
|
|
|
|
104 |
HYSD bar reinforcement in foundation complete as per drawing and
Technical Specifications. |
tonne |
Rs.35,460.00 |
|
|
|
(Rupees thirty five thousand four hundred sixty) only. |
|
|
|