DETAIL  ESTIMATE  FOR  CONSTRUCTION  OF  ASSAM  TYPE   BUILDING ( PCC FLOOR )

 

Sl no SOR No Items of Work Measurements Quantity Unit Rate Amount
No L B D Rs.    P Rs.      P
1 128 Earthwork in excavation in foundation trenches etc. not exceeding 2 meters depth including dressing of bottom and sides of trenches and subsequent filling as in column foundations, fence posts, etc. and disposal of all surplus soil as directed within a lead of 30 metres.
 
 
 
 
  (b) Hard Soil  ( pick work ). 11 0.60 0.60 1.30 5.148 cum 127.50 656.37
 
2 140 Providing and laying cement concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 40mm nominal size) excluding cost of centering and shuttering in -
 
 
  (a) All work upto foundation & plinth level. 11 0.60 0.60 0.10 0.396 cum 2830.40 1120.84
 
3 149 Providing and laying reinforced cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate  20mm nominal size) excluding cost of centering and shuttering and reinforcement in -
 
 
 
  (a) All work upto foundation & plinth level. 11 0.60 0.60 0.15 0.594 cum 3523.40 2092.90
  (b) Columns 11 1.50 0.20 0.20 0.660 cum 3758.80 2480.81
    (c) Kitchen platform 1 3.60 0.60 0.10 0.216 cum 3778.50 816.16
4 154 HYSD bars reinforcement for RCC work including straighthening, cutting, bending, placing in position and binding all complete.
 
 
  @ 100 Kg / cum of concrete 100 1.47 1.470 qtl 3342.10 4912.89
5 155 Centering and shuttering including strutting, propping, etc.  and removal of form works in -
 
  (a) Foundations, footings, bases of columns etc. for mass concrete.
  11 4 0.60 0.25 6.600 sqm 105.10 693.66
 
  (c) Columns, pillars, piers, abutments, posts and struts. 11 4 0.20 1.50 13.200 sqm 191.60 2529.12
  (e) Kitchen platform 1 1 3.60 0.60 2.160
  1 1 3.60 0.10 0.360
  2.520 sqm 218.70 551.12
6 213 Coursed rubble masonry with hard stone in cement mortar 1:6 (1 cement : 6 fine sand) including curing, etc. complete.                
                   
  (a) in foundation and plinth. 2 11.70 0.25 0.45 2.633
  2 7.20 0.25 0.45 1.620
  1 1.30 0.60 0.15 0.117
  1 1.00 0.30 0.15 0.045
  4.415 cum 2680.90 11834.83
7 130 Providing and filling stone aggregates of size below 90mm in plinth, etc. in layers not  exceeding 20 cms in depth,  consolidating each layer by ramming and watering and dressing complete.
  1 8.10 7.20 0.10 5.832
  1 3.60 4.50 0.10 1.620
  7.452 cum 994.90 7413.99
8 141 Providing and laying cement concrete 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40mm nominal size) excluding cost of centering and shuttering in -
 
 
  (a) All work upto foundation & plinth level. (floor) 1 8.10 7.20 0.075 4.374
  1 3.60 4.50 0.075 1.215
  5.589 cum 2545.90 14229.04
9 324 Cement concrete flooring 1:2:4 (1 cement : 2 sand : 4 well graded stone aggregate 20mm size) finished with a floating coat neat cement including cement slurry etc. complete but excluding the cost of nosing of steps etc.
 
 
 
  (a) 40mm thick = 5.589 / 0.075 74.520
  Deduct toilet floor -6.570
  67.950 sqm 191.40 13005.63
10 327 40 mm thick marble chips flooring rubbed and polished to granolithic finish with under layer 28mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone 10mm) and top layer of 12mm thick with white,  black, chocolate, grey, yellow or baroda green marble  chips of 7mm to 10mm nominal size laid in cement marble powder mix 3:1 (3cement : 1marble powder) by weight in proportion of 2 : 3 (2 cement powder mix : 3 marble chips) by volume including cement slurry etc. complete.
 
 
 
 
 
 
 
  Bathroom floor :
  (b) Light shade pigment with white cement. 1 2.70 1.50 4.050
  1 2.10 1.20 2.520
  6.570 sqm 693.10 4553.67
11 353 White glazed tiles of minimum thickness 5mm in flooring, treads of steps and landings laid on a bed of 10mm thick cement mortar 1 : 3 finished with flushed pointing in white cement.
  Bathroom skirting :
  2 2.70 1.50 8.100
  2 1.50 1.50 4.500
  2 2.10 1.50 6.300
  2 1.20 1.50 3.600
  Deduct Door 2 0.75 1.50 -2.250
  Deduct Window 2 0.90 0.50 -0.900
  19.350 sqm 858.10 16604.24
27 320 Providing and fixing a pair of flat iron brackets in concrete work while laying for jointing with timber post etc. including cost of bolts and nuts complete.
 
  11 pair 73.50 808.50
 
28 228 Providing 1st class local wood work dressed in frames of sill, upright, batten, post, beams, etc. as structural members fixed in position complete.
 
 
  Post 10 3.00 0.10 0.10 0.300
  1 2.50 0.10 0.10 0.025
  Upright 33 3.00 0.10 0.075 0.743
  9 1.00 0.10 0.075 0.068
  Sill 6 3.60 0.10 0.075 0.162
  5 4.50 0.10 0.075 0.169
  4 2.70 0.10 0.075 0.081
  3 0.90 0.10 0.075 0.020
  Horizontals 12 4.50 0.10 0.075 0.405
  15 3.60 0.10 0.075 0.405
  8 2.70 0.10 0.075 0.162
  9 0.90 0.10 0.075 0.061
  2.600
  Deduct Chaukhats -0.901
  1.699 cum 9884.00 16792.92
29 231 Providing Ist class local wood dressed in frames of chaukat for doors, windows, clerestory windows fixed in position.                
 
  D 2 2.10 0.10 0.075 0.032
  2 1.20 0.10 0.075 0.018
  D1 6 2.10 0.10 0.075 0.095
  6 0.90 0.10 0.075 0.041
  D2 4 2.10 0.10 0.075 0.063
  4 0.75 0.10 0.075 0.023
  W 18 1.80 0.10 0.075 0.243
  18 1.80 0.10 0.075 0.243
  W1 2 1.80 0.10 0.075 0.027
  3 0.90 0.10 0.075 0.020
  W2 4 1.00 0.10 0.075 0.030
  4 0.90 0.10 0.075 0.027
  V 3 0.60 0.10 0.075 0.014
  2 1.80 0.10 0.075 0.027
  0.901 cum 13709.00 12348.38
30 233 Providing 1st class local wood in trusses etc. including hoisting fixing in position supplying necessary fittings such as spikes bolts and nuts, nails etc and applying   wood preservative for unexposed surface etc. complete.
 
 
 
  Main truss 10 14.80 0.10 0.075 1.110
  Sub truss 5 4.28 0.10 0.075 0.161
  3 3.20 0.10 0.075 0.072
  10 2.10 0.10 0.075 0.158
  10 1.10 0.10 0.075 0.083
  4 3.30 0.10 0.075 0.099
  Purlins 12 4.52 0.05 0.075 0.203